MRc5 Construction and Demolition Waste Diversion

Develop a C&D materials management plan and document qualifying diversion with a final waste report. Both the diversion percentage and the required share of salvaged or source-separated material determine achievement.1

Points
See below
Applies to
BD+CID+C

Reviewed · Spot an error? Report it

Points

NC and Core and Shell: 1 point for at least 50% diversion with at least 10% of diverted material salvaged or source-separated to single-material recyclers; 2 points for at least 75% diversion with at least 25% of total diverted material meeting that condition.1

Exemplary performance: diverting at least 80% of total construction and demolition material, with at least half of the diverted material salvaged or sent source-separated to single-material recyclers, earns 1 exemplary performance point, claimed under Project Priorities (EP4).3

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • C&D materials management plan
  • Final waste management report with quantities, units, destinations, and disposal/diversion totals
  • Haul tickets and single-material recycler or salvage receipts supporting the report
  • Mixed-waste facility recycling-rate report and third-party verification, if used
  • Approved C&D plan in tenant guidelines for Core and Shell
  • Load receipt dates and corresponding monthly or annual facility-average recycling rates
  • Scale tickets or measured-volume records with the volume-to-weight conversion methodology

Worked example

Assume 100 metric tonnes of eligible waste, no salvage multiplier, 60 tonnes source-separated to single-material recyclers, and 40 tonnes disposed. Diversion = 60/100 × 100 = 60%. The source-separated share of diverted material is 60/60 × 100 = 100%. This meets the 1-point thresholds but not the 75% threshold for 2 points, assuming the plan and report requirements are also met.1

Requirements

Use one consistent basis, weight or volume, throughout the calculation. Source-separated recovery counts at 100%; off-site salvage for reuse receives a 200% diversion valuation. Mixed C&D recovery uses the facility average recycling rate, capped at 35% when it is not third-party verified. The July rating system classifies alternative daily cover and incineration/energy recovery as disposal.1

The October 2026 supplementary guidance treats wood from C&D recycling processing as biomass, distinct from waste-to-energy, and permits it as diversion for v5. Verify the material and destination fit that definition; this is not a general combustion allowance. The guidance applies to registrations on or after November 9, 2020 and does not replace applicable requirements or GBCI review.2

Use facility-average rates corresponding to the load receipt dates. The October guidance accepts scale weights or documented volume-to-weight conversion, while visual estimates are not accepted measurements.2

Exclude hazardous waste, excavated soil, land-clearing debris, and on-site reuse; the October guidance also excludes landscaping materials. On-site reuse belongs under MRc1. Core and Shell teams also place the approved C&D plan in tenant guidelines.12

FAQ

Can a mixed-waste facility's claimed recovery rate always be used?

No. Apply the facility average, but a rate without third-party verification is limited to 35% for this calculation.1

Does material reused on the project count here?

No. Exclude on-site reuse from MRc5 and evaluate it under MRc1. Off-site salvage is a different route.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · MRc5, printed pp. 146-147
  2. LEED Commingled Construction and Demolition Recycling Rate Reporting GuidanceOctober 2026 · pp. 1, 3-4, Table 1, Table 3 and Key Terms: Biomass
  3. USGBC LEED credit library: Construction and Demolition Waste Diversion: Exemplary Performance (EP4)Published Apr 21, 2025; retrieved November 8, 2026 · EP4 requirements

Maintained by VERTIQ, LEED software for consultants.