Credit Building Product Disclosure and Optimization - Material Ingredients
Use qualifying ingredient inventories or optimization while including in-scope furniture.1
- Points
- See below
- Applies to
- ID+C
- VERTIQ reference ID
- MRc5
Reviewed · Spot an error? Report it
Points
1 point per eligible option, maximum 2. The cost-based Option 2/3 contributions may combine toward the 25% threshold; a product meeting both is counted once.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Product/furniture inventory and complete accepted ingredient disclosures.
- Preparation checklist: Optimization/supply-chain verification, product costs, overlap controls and multiplier evidence.
Worked example
Assume Option 2 contributes $15,000 and separate Option 3 products contribute $12,000, with no overlap, from $100,000 total eligible project product cost. The combined share is ($15,000+$12,000)/$100,000 = 27%, above the combined cost threshold. This does not prove every product meets its reporting/verification criteria or earn a third point.1
Requirements
Option 1 needs at least 20 different permanently installed products from five manufacturers with an accepted ingredient-reporting method down to 0.1% (1,000 ppm). Accepted methods have their own content and hazard-disclosure criteria; a product name on a list is insufficient.1
Option 2 uses the specified ingredient optimization criteria for at least 25% by cost. Option 3 addresses verified manufacturer supply-chain programs at at least 25% by cost, with at least 99% by-weight ingredient documentation and the listed third-party program checks. Apply the stated combination, non-double-counting, locality and structure/enclosure rules. Include in-scope furniture and furnishings.1
FAQ
Can a product qualifying under both cost routes be counted twice?
No. Products meeting both Option 2 and Option 3 may only be counted once in the combined contribution.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Building Product Disclosure and Optimization - Material Ingredients; printed and PDF pp. 48-50