Credit Demand Response

Enable demand shedding or shifting with a qualified program or prepare for future participation.1

Points
1 to 2 points
Applies to
BD+C
VERTIQ reference ID
EAc4

Reviewed · Spot an error? Report it

Points

PointsRequirement
2Qualified participation
1The no-program infrastructure path

1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • DR provider agreement or utility correspondence
  • Peak-demand estimate
  • Load-shed and control-sequence plan
  • Meter/control specifications and commissioning test

Worked example

Assume estimated peak demand is 1,000 kW. The participation commitment must cover at least 1,000 x 10% = 100 kW, supported by the DR plan and tested capability.1

Requirements

Where a program is available, enroll for at least one year with multiyear renewal intent and commit at least 10% of estimated peak electricity demand. Provide external-signal capability, a DR plan and commissioning including a full test. Without a program, provide the specified interval metering, control capability, a plan to shed at least 10% of estimated peak electricity demand, commissioning including a full test, and utility contact. On-site generation alone does not meet the credit intent.1

FAQ

Can a backup generator alone satisfy Demand Response?

No. The credit is directed at demand shedding or shifting; on-site generation alone does not meet its intent.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4 BD+C Rating SystemUpdated July 25, 2019 · Demand Response, printed/PDF pp. 78

Maintained by VERTIQ, LEED software for consultants.