Credit Direct Exterior Access
Healthcare projects give patients direct access to an exterior courtyard, terrace, garden or balcony.1
Reviewed · Spot an error? Report it
Points
1 point, Healthcare only.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Area and patient calculations, with any excluded patient groups
- Site plan showing accessible outdoor areas, area takeoffs, building air exhausts, exterior exhaust vents, access points and distances to outdoor areas
Worked example
Assume a Healthcare project has 100 included inpatients and 20 qualifying outpatients. Exterior access for 80 and 16 gives 80% for each group, above 75%. Space for those 96 patients at 0.5 m2 each = 48 m2. Separation and nonsmoking conditions are checked separately.1
Requirements
Healthcare only. Provide direct access to an exterior courtyard, terrace, garden or balcony. The space must be at least 5 square feet (0.5 square meters) per patient for 75% of all inpatients and 75% of qualifying outpatients whose clinical length of stay exceeds four hours.1
Patients whose length of stay exceeds four hours and whose treatment makes them unable to move, such as emergency, stage 1 surgical recovery and critical care patients, may be excluded. Places of respite outside the building envelope that meet the Places of Respite credit may be included if they are immediately adjacent to clinical areas or have direct access from inpatient units.1
Qualifying spaces must be designated nonsmoking and be more than 100 feet (30 meters) from building exhaust air locations, loading docks and roadways with idling vehicles.1
FAQ
Can inpatient and outpatient access percentages be averaged together?
No. The requirement states 75% for inpatients and 75% for qualifying outpatients, so check each group on its own.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Direct Exterior Access, printed/PDF p. 49
- LEED v4.1 BD+C GuideNovember 2025 · Printed and PDF p. 6 (BD+C scorecard) and p. 75 (credit heading)
Maintained by VERTIQ, LEED software for consultants.